TDOT reaches halfway mark on bridge repairs

TDOT reaches halfway mark on bridge repairs (Image 1)
TDOT reaches halfway mark on bridge repairs (Image 1)

The Tennessee Department of Transportation reached the halfway mark on the ongoing bridge repair work on Interstate 24.

Crews have worked for a total of seven weekends to install concrete panels.

TDOT officials said four separate crews are working around the clock during the weekend on the project despite the intense heat.

The $8.6 million project is expected to be complete August 31.